WhiteFiber (Nasdaq: WYFI) has closed a $60 million all-cash purchase of two industrial sites in Yadkin County, North Carolina, labeled NC-2 and NC-3, according to theenergymag.com. The sites lie roughly 55 miles from the firm's current NC-1 campus and should initially offer 60 MW of gross grid capacity, with potential to reach 200 MW within seven years. The company is aiming for a ready-for-service date in late 2027 and says it has received non-binding letters of intent from prospective tenants, among them investment-grade firms.
Meanwhile, the NC-1 site in Madison has run behind schedule: problems commissioning switchgear pushed back the move to full contracted billing past the August target. Presently 35 of the 40 MW of IT capacity there is running. WhiteFiber also says the initial build-out is largely finished and is within its original budget.
why it matters
The deal is small for the sector as a whole, but it signals WhiteFiber's push to grow its AI infrastructure. Key risks are the new sites' dependence on utility power and the 2027 timeline, while the NC-1 delay shows that execution on current projects has not been smooth.
tags
instruments
sources
- WhiteFiber Acquires Two North Carolina Sites for $60 Million Data Center Expansion — theenergymag.com, 3 November 2026 at 21:40 UTC
prepared by the newsmetry newsroom with ai assistance from the sources listed below. not investment advice.
alerts on your topics, the morning digest and the api — in your account.
get stories in real time ↗